Question:

We entered the wrong revenue start / end date for an RC, how do I fix this in RevPro? 





If you found my answer helpful, please give me a kudo ↑
Help others find answers faster by accepting my post as a solution √

1 ACCEPTED SOLUTION

Accepted Solutions
Highlighted
Zuora Support

Re: Change Revenue Start / End Date

Answer:

If the line is 0% recognized, you can defer the line, gather an SO update with the correct dates, and this will update the start / end date for you. 





If you found my answer helpful, please give me a kudo ↑
Help others find answers faster by accepting my post as a solution √

View solution in original post

1 REPLY 1
Highlighted
Zuora Support

Re: Change Revenue Start / End Date

Answer:

If the line is 0% recognized, you can defer the line, gather an SO update with the correct dates, and this will update the start / end date for you. 





If you found my answer helpful, please give me a kudo ↑
Help others find answers faster by accepting my post as a solution √

View solution in original post