02-11-2019
05:46 PM
Question: In the new RevPro UI, where can I start or stop the scheduler?
Solved! Go to Solution.
Labels:
1 ACCEPTED SOLUTION
Accepted Solutions
- Mark as New
- Bookmark
- Subscribe
- Permalink
- Email to a Friend
- Report Inappropriate Content
02-11-2019
06:01 PM
02-11-2019
06:01 PM
Solution:
Complete the following steps to start or stop the scheduler in the new RevPro UI:
- Navigate to Setups > Application.
- Open the side menu and click Background Jobs.
- On the Background Jobs page, click Schedule Manager
. If the scheduler is already started, the Stop Scheduler window is displayed. Otherwise, the Start Scheduler window is displayed.
- To stop the scheduler, click Stop in the Stop Scheduler window, confirm your selection and click OK.
- To start the scheduler, specify the scheduler repeat interval and click Start in the Start Scheduler window
1 REPLY 1
- Mark as New
- Bookmark
- Subscribe
- Permalink
- Email to a Friend
- Report Inappropriate Content
02-11-2019
06:01 PM
02-11-2019
06:01 PM
Solution:
Complete the following steps to start or stop the scheduler in the new RevPro UI:
- Navigate to Setups > Application.
- Open the side menu and click Background Jobs.
- On the Background Jobs page, click Schedule Manager
. If the scheduler is already started, the Stop Scheduler window is displayed. Otherwise, the Start Scheduler window is displayed.
- To stop the scheduler, click Stop in the Stop Scheduler window, confirm your selection and click OK.
- To start the scheduler, specify the scheduler repeat interval and click Start in the Start Scheduler window